Thursday, October 18, 2018

Site visit, Pour Bent 1 Cap

 Onsite to pour Bent 1 cap, looked over form work and steel placement.

 All looks good, tested concrete and started pouring bent 1 cap.

 Pour went good and I made three cylinders.

Wednesday, October 17, 2018

Site visit, Pour Bent 2 Cap


 Onsite to Pour Bent 2 cap, I checked form work and steel placement.

 Steel and forms look good, I tested the concrete and we started pouring.

Pour went good, made three cylinders and will be back tomorrow to pour Bent 1 cap.

Friday, October 12, 2018

Site visit, Seating Piling

 Onsite today to Seat Piling, Crane was onsite and was getting setup.
 Seated Bent 2 piling first, Pile drove some past pre-bore


 Finished seating Bent 2 and have to drive crane around to Bent 1
 Had to Add to the pad for the crane for Bent 1


 Crane is setup and started seating piling

 All piling are seated and Bent 1 piling drove past plan as well.

Wednesday, October 10, 2018

Site visit, Day Two Pre-Bore

Day two has started,

 Drilling is going good.



 Finished drilling and contractor started placing piling and gravel in holes









 Will be back to seat piling.


Tuesday, October 9, 2018

Site visit, Pre-Bore Day

 Arrow Drilling was onsite to Bore the holes for the Piling.
 Piling is onsite and match the paperwork.



 Each hole is taking two hours to drill plus or minus









 Just a view from other side






 All pile are in place and now moving to the other side, Drill rig is setup and started on first hole.
 Placing Gravel in holes to Seat piling tomorrow.




 A heavy down pour delayed the drilling for a few minutes.






 Calling it a day, will return in the morning to finish the pre-bore.