Site visit, Seating Piling

 Onsite today to Seat Piling, Crane was onsite and was getting setup.
 Seated Bent 2 piling first, Pile drove some past pre-bore


 Finished seating Bent 2 and have to drive crane around to Bent 1
 Had to Add to the pad for the crane for Bent 1


 Crane is setup and started seating piling

 All piling are seated and Bent 1 piling drove past plan as well.