Contractor placed Post to the end of the bridge for fence.
Cutting in side slopes
removing form work from back walls and drilling in post holes.
Placing the final rip rap around bridge.
cutting in ditches
Drilling holes for post, will set them tomorrow.
Friday, November 16, 2018
Friday, November 9, 2018
Site visit, Roadway Compaction
Contractor was building roadway, compaction was good for the most part. Some areas are soft and will need to be removed and fixed.
Soft spot
another place
Cutting in ditches
Stopping for the day, will start back up tomorrow.
Soft spot
another place
Cutting in ditches
Stopping for the day, will start back up tomorrow.
Wednesday, November 7, 2018
Site visit, pour back walls
Onsite today to pour the back walls, I checked the steel placement and form work.
Concrete arrived and I tested it. we poured Bent 1 first.
Finished bent 1 and moved to Bent 2.
Both pours went good, made three cylinders for each wall.
Concrete arrived and I tested it. we poured Bent 1 first.
Finished bent 1 and moved to Bent 2.
Both pours went good, made three cylinders for each wall.
Monday, November 5, 2018
Wednesday, October 24, 2018
Site visit, Set Beams
Onsite to set Beams, Crane was onsite and getting setup when I arrived.
First beam arrived, all but two was onsite to be set.
All beams are set and all look good, contractor will start drilling and grouting beams.
First beam arrived, all but two was onsite to be set.
All beams are set and all look good, contractor will start drilling and grouting beams.